| The Township Engineering Department serves as a liaison between the Township and Union County on various County projects. COUNTY PROJECTS
• Resurfacing of Vauxhall Road, Completed Fall 2004
• Intersection Improvements at Stanley Terrace and Burnet Avenue, completed Summer
2005
• Intersection Improvements at Vauxhall Road and Burnet Avenue, completed Summer 2005
• Union Avenue, Milltown Road, and Vauxhall Road Bridges; completed Spring 2005
• Salem Road Bridge Replacement, completed Summer 2005
• Resurfacing Chestnut Street; completed Summer 2005
• Construction of 2 new intersections: W. Chestnut & Stuyvesant, Stuyvesant & Stanley
Design 2007
• Resurfacing Stuyvesant Avenue from Vauxhall Road to Irvington line, Summer 2007
• Resurfacing Chestnut Street from Westfield Avenue to Sumner Avenue, Summer 2007
STATE PROJECTS
• Route 82 Streetscape Project - construction 2006-2008
• North Avenue resurfacing - completed Fall 2005
• Route 22 & Michigan Avenue Drainage Improvement Project - in design phase
• Route 22 & Madison Avenue Drainage Improvement Project - in design phase
• Route 78 widening and reconstruction - construction thru Sept. 2007 |